Full home interiors in India typically cost between ₹1,000 and ₹4,000 per square foot of carpet area, depending on materials and finish level. At a mid range specification, a 2BHK usually lands between ₹6 lakh and ₹15 lakh, and a 3BHK between ₹10 lakh and ₹25 lakh.
The number that varies most between two quotations is rarely the rate. It is what each quotation leaves out. This article covers both: what things actually cost, and where the gaps sit.
Cost Per Square Foot by Finish Level
| Level | Per sq ft of carpet area | What it typically means |
| Essential | ₹1,000 to ₹1,500 | MR grade plywood or MDF, laminate finishes, basic hardware, limited false ceiling |
| Mid range | ₹1,500 to ₹2,500 | BWR or BWP plywood in wet areas, better laminates or acrylic, branded hardware, standard false ceiling and lighting |
| Premium | ₹2,500 to ₹4,000 | BWP plywood throughout, acrylic or PU finishes, premium hardware, designed lighting, veneer elements |
| Luxury | ₹4,000 and above | Custom joinery, imported hardware and surfaces, natural stone, specialist lighting, bespoke furniture |
Confirm these against Brandroot’s own rate card before publishing.
The most important line in this table is the unit. Rates should be quoted per square foot of carpet area, which is the usable floor area as defined under RERA. Some quotations are calculated on built up or super built up area, which is a larger number and therefore produces a lower looking rate for the same work.
Two firms quoting ₹1,500 per square foot are not quoting the same thing if one is measuring 1,000 sq ft of carpet area and the other 1,250 sq ft of built up. The second quotation is twenty five percent more expensive while appearing identical.
Always ask which area basis the rate applies to, and compare the total figure rather than the rate.
Budget by Home Size
| Home size | Typical carpet area | Essential | Mid range | Premium |
| 1 BHK | 450 to 650 sq ft | ₹3.5L to ₹6L | ₹6L to ₹10L | ₹10L and above |
| 2 BHK | 700 to 1,100 sq ft | ₹5L to ₹9L | ₹9L to ₹18L | ₹18L and above |
| 3 BHK | 1,100 to 1,600 sq ft | ₹8L to ₹14L | ₹14L to ₹30L | ₹30L and above |
| 4 BHK or villa | 1,800 sq ft and above | ₹14L and above | ₹25L and above | ₹45L and above |
Ranges are wide because scope varies enormously. A 3BHK where only the kitchen and wardrobes are done sits at the bottom of the range. The same 3BHK with full false ceiling, designed lighting, wall panelling, loose furniture and a study lands near the top.
What Individual Components Cost
| Component | Typical range | What moves the price |
| Modular kitchen | ₹1.5L to ₹6L and above | Size, carcass material, shutter finish, hardware brand, countertop |
| Wardrobe | ₹1,200 to ₹2,500 per sq ft of wardrobe face | Finish, internal fittings, sliding versus openable |
| False ceiling | ₹60 to ₹200 per sq ft | Plain versus designed, cove lighting, gypsum versus POP |
| Painting | ₹15 to ₹40 per sq ft | Emulsion grade, number of coats, texture or accent work |
| TV and media unit | ₹40,000 to ₹1.5L | Size, storage, finish, integrated lighting |
| Pooja unit | ₹30,000 to ₹1.5L | Material, carving, size |
| Study or work desk | ₹25,000 to ₹80,000 | Size, storage, integration with wardrobes |
| Designer or consultancy fee, where charged separately | 5 to 12 percent of project value | Scope of design involvement and drawings provided |
Kitchens and wardrobes together typically account for half to two thirds of a full home interior budget. If the budget is tight, these are where quality spending pays back, because they take daily use and are the hardest to redo later.
Our turnkey home interior services are quoted component wise so you can see exactly where the budget sits.
Materials: Where Cheap Quotations Save Money
A quotation that comes in far below the others is not usually dishonest. It is usually specifying differently. These are the four places it happens.
Carcass material. Plywood grades are not interchangeable.
| Material | Suitable for | Notes |
| Particle board and MDF | Low moisture areas, budget builds | Poor water resistance, limited screw holding |
| HDHMR | Mid budget, better than MDF | Reasonable in dry areas |
| MR grade plywood | Bedrooms, living areas | Moisture resistant only, not waterproof |
| BWR grade plywood | General use, mildly wet areas | Boiling water resistant |
| BWP or marine grade plywood | Kitchen, bathroom vanities, utility | Boiling water proof, the correct choice near water |
Using MR grade plywood in a kitchen base unit saves money at installation and fails within a few years. This single substitution is the most common difference between a low quote and a fair one.
Shutter finish. Laminate is the most economical, followed by acrylic, PU, lacquered glass and veneer. The price gap between laminate and acrylic across a full home is substantial.
Hardware. Hinges, channels and lift-up mechanisms are roughly fifteen to twenty five percent of modular cost and are invisible in photographs. Branded hardware carries a warranty and survives daily use. Unbranded hardware is where an aggressive quote finds most of its savings.
Shutter thickness and edge banding. Thinner shutters and cheaper edge banding are difficult to spot at handover and obvious after two monsoons.
Ask for the brand and grade of every material in writing. A quotation that says “premium plywood” without a grade is not a specification.
What Is Usually Not Included
This is where budgets overrun. Check each line against your quotation.
- GST, charged at the applicable rate on interior work. Quotations stated as exclusive of GST are meaningfully higher than they appear
- Civil work, including demolition, wall changes, plumbing relocation, waterproofing
- Electrical work, including new points, wiring changes and DB modifications
- False ceiling and painting, sometimes quoted separately
- Appliances, including chimney, hob, oven, refrigerator
- Loose furniture, including sofas, beds, dining sets and chairs
- Curtains, blinds and soft furnishings
- Decorative light fixtures, as distinct from cove and profile lighting
- Society charges, including lift usage, labour entry permissions and debris removal
- Site supervision or project management, where charged separately
Two quotations can differ by several lakh purely on which of these lines sit inside the number. Ask every firm to mark each item as included, excluded or provisional.
Payment Structure and Timeline
A typical payment schedule looks like this:
| Stage | Typical share |
| Booking or design advance | 10 percent |
| On design sign off, before production | 40 to 50 percent |
| On material delivery to site | 30 to 40 percent |
| On completion and handover | 5 to 10 percent |
Retain a meaningful final payment until handover and snag closure. A schedule that requires close to the full amount before installation removes your only leverage if something is wrong.
Timeline for a typical 2BHK or 3BHK:
| Stage | Duration |
| Design development and finalisation | 2 to 4 weeks |
| Factory production of modular units | 3 to 5 weeks |
| Site installation | 2 to 4 weeks |
| Civil and electrical work, where applicable | Adds 2 to 4 weeks, usually in parallel |
| Snagging and handover | 1 week |
Realistically, 45 to 75 days from design sign off for a full home, longer if civil work is extensive. Anyone promising a full 3BHK in three weeks is either doing very limited scope or is going to miss the date.
You can see how projects are sequenced in practice across our completed home projects.
How to Compare Two Quotations Properly
- Confirm the area basis. Carpet, built up or super built up.
- Ask for a component wise breakdown, not a lump sum.
- Check material grades and brands for carcass, shutters, hardware and countertop.
- Mark every exclusion. Use the list above as a checklist.
- Confirm whether GST is included in the stated figure.
- Ask for the warranty in writing, including what it covers and for how long.
- Get the timeline in writing, with stage dates.
- Check who supervises the site and how often.
- Confirm the payment schedule and how much is retained until handover.
- Ask to visit a completed project or an ongoing site.
Point ten is the most useful and the least used. Photographs are styled and rendered. A two year old completed home tells you what the work looks like after real use, which is the only quality signal that matters.
Warning Signs
- A quotation produced without a site measurement
- No written bill of quantities or scope document
- Material described by adjective rather than grade and brand
- No warranty document, or a warranty with no named coverage
- More than half the value demanded before production starts
- Design changes agreed verbally rather than in writing
- A rate quoted without stating the area basis
Frequently Asked Questions
How much does 2BHK interior design cost in India?
A 2BHK of 700 to 1,100 sq ft carpet area typically costs ₹5L to ₹9L at an essential specification, ₹9L to ₹18L at mid range, and above ₹18L for premium finishes. The final figure depends heavily on whether false ceiling, painting, loose furniture and lighting are inside the scope.
What is the interior design cost per square foot in India?
Roughly ₹1,000 to ₹1,500 per sq ft for essential work, ₹1,500 to ₹2,500 for mid range, ₹2,500 to ₹4,000 for premium and above ₹4,000 for luxury. Always confirm whether the rate applies to carpet area or built up area, since this alone can change the total by twenty five percent.
How much does a modular kitchen cost?
Commonly ₹1.5L to ₹6L and above. The main variables are size, carcass material, shutter finish, hardware brand and countertop. BWP plywood is the appropriate carcass material for a kitchen, and specifying anything less is where cheap quotes save money.
Is GST included in interior design quotations?
Frequently not. Always ask whether the figure quoted is inclusive or exclusive of GST, because the difference is significant on a project of this size and it is a common source of dispute at the final invoice.
How long does a full home interior project take?
Typically 45 to 75 days from design sign off for a 2BHK or 3BHK, comprising two to four weeks of design finalisation, three to five weeks of production and two to four weeks of installation. Extensive civil work extends this.
Why do interior quotations vary so much for the same home?
Mostly because of scope and material grade rather than margin. Differences come from which items are excluded, which plywood grade is specified, whether hardware is branded, whether GST is included, and which area basis the rate is applied to. Compare specifications, not headline figures.
Should I do interiors before or after moving in?
Before, wherever possible. Working in an occupied home extends the timeline, restricts working hours in most societies, and adds cost for protection and cleaning. If the home is already occupied, expect a longer schedule.
What should I prioritise if my budget is limited?
Kitchen and wardrobes, in that order. They take the most daily use, they are the most difficult and disruptive to redo later, and they carry the most value at resale. False ceiling, decorative panelling and loose furniture can be added in a later phase.
Get a Number Based on Your Actual Home
The ranges in this article are useful for setting expectations. They are not a quotation, because scope and site conditions move the figure more than any published rate can capture.
If you want a real number, share your floor plan and requirements and we will give you a component wise breakdown with every inclusion and exclusion marked, before anyone visits to sell you anything.